Future Projects/Study Areas

Big Valley Court

Project Status: Study in progress

Project Summary: This area is under investigation.  Huntertown has declined connection.

Project Information:

Number of Connections: TBD

Design Firm: TBD

Construction Contractor: TBD

Project Cost: TBD

Budget:

“As-Bid” Construction Contract: TBD
Change Order #1: TBD
Current Construction Contract: TBD

Canyon Run extended

Project Status: Engineering study complete

Project Summary: The project cost feasibility and resident votes are under review for this area.

Project Information:

Number of Connections: 16

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: TBD

Project Cost:

Estimated Collection Construction Costs: $760,000

Contingency (10%): $76,000

Non-Construction Costs (20%): $164,000

Total Estimated Project Costs: $1,000,000

 

Community of Edgerton

Project Status: Study in progress

Project Summary: This area is being investigated for the construction of its own treatment facility.

Project Information:

Number of Connections: TBD

Design Firm: TBD

Construction Contractor: TBD

Project Cost: TBD

Budget:

“As-Bid” Construction Contract: TBD
Change Order #1: TBD
Current Construction Contract: TBD

Community of Williams

Project Status: Study in progress

Project Summary: This area is being investigated for the construction of its own treatment facility.

Project Information:

Number of Connections: TBD

Design Firm: TBD

Construction Contractor: TBD

Project Cost: TBD

Budget:

“As-Bid” Construction Contract: TBD
Change Order #1: TBD
Current Construction Contract: TBD

Community of Lake Everett

Project Status: Engineering study complete

Project Summary: The project cost feasibility and resident votes are under review for this area.

Project Information:

Number of Connections: TBD

Design Firm: TBD

Construction Contractor: TBD

Project Cost:

Estimated Collection Subtotal Construction Costs: $1,988,000

Contingency (10%): $198,000

Non-Construction Costs (20%): $434,000

Total Estimated Project Costs: $2,620,000

Zanesville regional

Project Status: Study area

Project Summary: This area is under investigation for a potential future project.

Project Information:

Number of Connections: TBD

Design Firm: TBD

Construction Contractor: TBD

Project Cost: TBD

Budget:

“As-Bid” Construction Contract: TBD
Change Order #1: TBD
Current Construction Contract: TBD

2018-2019 Construction

Community of Maples

Project Status: In Construction

Project Summary:

ACRWSD submitted a request for financing through the Indiana Department of Environmental Management (IDEM) State Revolving Fund (SRF) program. This was done in an effort to receive the SRF low interest financing as well as potential grant funding.  Final project costs were approximately $10.6M with the District receiving grant/inter-agency funding assistance of approximately $4.7M with a final loan of approximately 5.9M.

Formal design work has been completed, the project was bid in late May and ACRWSD has recently awarded the construction contract to Underground Contractors, Inc. from New Haven, IN. The contractor is in the process of initiating construction of the sewer system and has an official notice to proceed with the work dated October 29, 2018.

Project Information:

Number of Connections: 82

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: Underground Contractors, Inc.

Project Cost: TBD

Total Estimated Project Costs: TBD

Dupont Road West

Project Status: Not in Construction

Project Summary:

ACRWSD submitted a request for financing through the Indiana Department of Environmental Management (IDEM) State Revolving Fund (SRF) program. This was done in an effort to receive the SRF low interest financing as well as potential grant funding.  Final project costs were approximately $10.6M with the District receiving grant/inter-agency funding assistance of approximately $4.7M with a final loan of approximately 5.9M.  

Formal design work has been completed, the project was bid in late May and ACRWSD has recently awarded the construction contract to Underground Contractors, Inc. from New Haven, IN. The contractor is in the process of initiating construction of the sewer system and has an official notice to proceed with the work dated January 07, 2019.

Project Information:

Number of Connections: 29

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: Underground Contractors, Inc.

Project Cost: TBD

Total Estimated Project Costs: TBD

Hoagland Rehab

Project Status: Construction in Process

Project Summary:

ACRWSD submitted a request for financing through the Indiana Department of Environmental Management (IDEM) State Revolving Fund (SRF) program. This was done in an effort to receive the SRF low interest financing as well as potential grant funding.  Final project costs were approximately $10.6M with the District receiving grant/inter-agency funding assistance of approximately $4.7M with a final loan of approximately 5.9M.

Formal design work has been completed, the project was bid in late May and ACRWSD has recently awarded the construction to:

Contract (A) Lift Stations and Flow Equalization

Construction Contractor: Thieneman Construction,Inc.

Notice to proceed with the work: November, 26, 2018

Contract (B) South of the Flow Meter – Project 1

Construction Contractor: S&S Directional Boring, Ltd.

Notice to proceed with the work: November, 12, 2018

Contract (B) North of the Flow Meter – Project 2

Construction Contractor: Rothenberger Company, Inc.

Notice to proceed with the work: October 29, 2018

Project Information:

Design Firm: Commonwealth Engineers, Inc.

Project Cost: TBD

Total Estimated Project Costs: TBD

Lafayette Center, Indianapolis Road

Project Status: Not in Construction

Project Summary:

ACRWSD submitted a request for financing through the Indiana Department of Environmental Management (IDEM) State Revolving Fund (SRF) program. This was done in an effort to receive the SRF low interest financing as well as potential grant funding.  Final project costs were approximately $10.6M with the District receiving grant/inter-agency funding assistance of approximately $4.7M with a final loan of approximately 5.9M.

Formal design work has been completed, the project was bid in late May and ACRWSD has recently awarded the construction contract to API Construction, Inc. from LaOtto, IN. The contractor is in the process of initiating construction of the sewer system and has an official notice to proceed with the work dated November 26, 2018.

Project Information:

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: API Construction, Inc.

Project Cost: TBD

Total Estimated Project Costs: TBD

Monroeville Road-Marion Road-Thompson Road

Project Status: Not in Construction

Project Summary:

ACRWSD submitted a request for financing through the Indiana Department of Environmental Management (IDEM) State Revolving Fund (SRF) program. This was done in an effort to receive the SRF low interest financing as well as potential grant funding.  Final project costs were approximately $10.6M with the District receiving grant/inter-agency funding assistance of approximately $4.7M with a final loan of approximately 5.9M.

Formal design work has been completed, the project was bid in late May and ACRWSD has recently awarded the construction contract to S&S Directional Boring, LTD from Bryan, OH. The contractor is in the process of initiating construction of the sewer system and has an official notice to proceed with the work dated November 12, 2018.

Project Information:

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: S&S Directional Boring, LTD

Project Cost: TBD

Total Estimated Project Costs: TBD

2017-2018 Construction

Andar-Trail-Pion Road

Project Status: Complete

Project Summary: All work was substantially complete as of October 13, 2017 and the system is ready for homeowner connections. The project was completed slightly over budget; however, the impact of two additional connections reduced the connection per user. Certified ‘Notice to Connect’ were issued November 22, 2017 giving homeowners 90 days to get hooked up to the sewers.

Project Information: 

Number of Connections: 26

Design Firm: Wessler Engineering, Inc.

Construction Contractor: S&S Directional Boring, LTD

Final Construction Costs:

“As-Bid” Construction Contract: $371,186.00

Change Order No. 1: $7,278.90
Final Contract Amount: $378,464.90

Carrol Road-Hand Road-Carroll Lynn Drive

Project Status: Complete

Project Summary: All work was substantially complete as of Decemeber 7th, 2017. The project was completed slightly under budget. Certified ‘Notice to Connect’ were issued March 15, 2018 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 24

Design Firm: Wessler Engineering, Inc.

Construction Contractor: Fleming Excavating, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $1,306, 554.23
Change Order No. 1: ($ 3,848.14)

Final Contract Amount: $ 1,302,706.09

Community of Poe

Project Status: Construction is complete for west side of St. Mary’s river.  East side is in progress.

Project Summary: Construction began on March 13th, 2017. Outside of the failed river crossing, the work associated with the project is primarily complete. Poe pump station passed its start-up inspections on March 6th, 2018 and the project on the west side of the St. Mary’s River is now considered complete. Certified ‘Notice to Connect’ were issued March 19th, 2018 giving homeowners 90 days to get hooked up to the sewers.

Work is complete at the Mill Road Estates pump station and the pump station passed its start-up inspection on May 1st.

The remaining outstanding item is the completion of the force main. In order to complete the crossing, the contractor has engaged a specialty boring contractor to complete the rock-like nature of the soils under the river. This work is scheduled to begin at the end of August.

Assuming the river crossing work is completed in a timely manner, we anticipate being in a position to order Connections on the east side of the river in late September.

Project Information:

Number of Connections: 80

Design Firm: Engineers, Inc.

Construction Contractor: Rothenberger Company

Budget:

“As-Bid” Construction Contract: $1,815,705.48

Change Order No. 1-3: $114,264.85
Billed as of 07/31/18: 1,916,264.85

Work Completed= 99.2% Contract Value

Glen Elm-Leo Road-Sonata Drive

Project Status: In Progress

Project Summary: Construction began in November 2017. Contractor completed construction of the collection system and grinder pump stations in June.  Pressure testing of the collection system is complete and all lines have passed.  Start-up inspections of the grinder pump stations and the main pump station were performed on June 28 and 29.  Punch list items with respect to the main pump station based on the start-up inspections have been distributed to the contractor and subsequent work is in the process of being completed.  Once this work is complete, we will submit As-Built drawings, RCI’s maintenance bond and completion affidavit to the City for their formal acceptance.  We anticipate being in a position to order connections in the project area in mid to late August.

Project Information:

Number of Connections: 63

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: Rothenberger Company

Budget:

“As-Bid” Construction Contract: $1,235,425.50
FTW Oversizing Commitment: $143,431.82

Billed as of 07/12/18: $1,135,625.50

Work Completed: 91.3% Contract Value

2016 Construction

Wallen Road-Wallen Community

Project Status: Complete

Project Summary: All work was substantially complete as of June 15, 2016 and the system is ready for homeowner connections. The project was completed under budget. Certified ‘Notice to Connect’ were issued July 11, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 46

Design Firm: Jones Petrie Rafinski Corp.

Construction Contractor: Rothenberger Company, Inc.

Final Construction Costs:

“As-Bid” Construction Contract:  $748,534.35
Change Order #1-2:  ($33,360.75)
Final Contract Amount:  $715,173.60

HCC, Berneway & Yoder – Contract “A”

Project Status: Complete

Project Summary: All work was substantially complete as of July 1, 2016 and the system is ready for homeowner connections. The project was completed slightly over budget. Certified ‘Notice to Connect’ were issued July 13, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections:152

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: Underground Contractors Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $2,261,815.00
Change Order #1-2: $16,712.00
Final Contract Amount: $2,278,527.00

HCC, Berneway & Yoder – Contract “B”

Project Status: Complete

Project Summary: All work was substantially complete as of September 16, 2016 and the system is ready for homeowner connections. The project was completed over budget; however, the impact of the additional connections actually reduced the connection cost per user. Certified ‘Notice to Connect’ were issued September 7, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 75

Design Firm: Commonwealth Engineers, Inc.

Construction Contractor: Rothenberger Company, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $886,158.35
Change Order #1: $84,698.00
Current Construction Contract: $970,856.35

Lower Huntington-Whippoorwill Drive

Project Status: Complete

Project Summary: All work was substantially complete as of September 20, 2016 and the system is ready for homeowner connection.  The project was completed under budget. Certified ‘Notice to Connect’ were issued Ocotber 20, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 40

Design Firm: Wessler Engineering, Inc.

Construction Contractor: Rothenberger Company, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $647,744.05
Change Order #1 & #2: ($34,630.80)
Final Contract Amount: $613,113.25

Hursh-Tonkel-Crawford Road

Project Status: Complete

Project Summary: All work was substantially complete as of September 16, 2016 and the system is ready for homeowner connections. The project was completed slightly over budget; however, the impact of the additional connections actually reduced the connection cost per user. Certified ‘Notice to Connect’ were issued October 13, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 86

Design Firm: Wessler Engineering, Inc.

Construction Contractor: Underground Contractors, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $1,210,610.00
Change Order #1: ($ 46,592.30)
Current Construction Contract: $1,164,017.70

Goshen-Cook-Fritz-Steele

Project Status: Complete

Project Summary: All work was substantially complete as of September 16, 2016 and the system is ready for homeowner connections. The project was completed slightly over budget; however, the impact of the additional connections actually reduced the connection cost per user. ‘Notice to Connect’ were issued October 13, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 86

Design Firm: Wessler Engineering, Inc.

Construction Contractor: Underground Contractors, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $1,210,610.00
Change Order #1: ($ 46,592.30)
Current Construction Contract: $1,164,017.70

Gerdings-Kroemer-Leesburg

Project Status: Complete

Project Summary: All work was substantially complete as of September 13, 2016 and the system is ready for homeowner connections. The project was completed slightly over budget; however, the impact of the additional connections actually reduced the connection cost per user. Certified ‘Notice to Connect’ were issued October 13, 2016 giving homeowners 90 days to get hooked up to the sewers.

Project Information:

Number of Connections: 64

Design Firm: Jones Petrie Rafinski Corp.

Construction Contractor: CSU, Inc.

Final Construction Costs:

“As-Bid” Construction Contract: $1,112,412.67
Change Order #1-2: 23,287.53
Current Construction Contract: $1,135,700.20